Construction Progress Report

UA&P Cebu Expansion
Punch List Status

12F Latitude Corporate Center, Cebu City

April 27, 2026
UA&P Cebu Campus
GA · Ng Khai · FASCLAD · CWC · Kintar · Walls in Motion
93
Total Items
Master punch list
49
Completed
58% done
20
In Progress
24% active
16
Not Started
19% pending
28
High Priority
33% of items
Overall Completion
58% complete · 85 items
58%
24%
19%
Completed 49
In Progress 20
Not Started 16
Overall Progress — Visual Breakdown
58%
Complete
Completed
49 58%
In Progress
20 24%
Not Started
16 19%
Total Items 85

Watch List

8 items requiring attention
01
Furniture — All Areas
3-month lead time; delivery still pending across all spaces
Multipurpose HallLobbyPantryHuddle Room
In Progress CWC
02
Acoustic Panels — Caseroom & Multipurpose Hall
Material stuck in customs; supplier delivery pending on site
CaseroomMultipurpose Hall
Completed GA
03
Glass Partitions & Doors
Waiting for glass delivery from China
Director's OfficeCaseroom AV RoomMultipurpose Hall
In Progress FASCLAD
04
Operable Wall Partitions - for JFS approval
Down payment pending; supplier to conduct site inspection this week
Meeting RoomMultipurpose Hall
In Progress Walls in Motion
05
AV & Auxiliary Devices — Multiple Items
Projector screen, PTZ camera (installed), switch devices (installed), internet device — all awaiting delivery
CaseroomLobbyServer Room
In Progress Ng Khai / DATCHE
06
Fire Extinguishers — All Areas
To be purchased by UA&P first before Kintar can proceed with installation
CaseroomLobbyPantryMultipurpose HallServer Room
Not Started Kintar / UA&P
07
Linear Light from Landlite
2-month lead time; expected delivery end of May 2026
Caseroom
In Progress Landlite
08
Occupancy Permit — MEPF As-Built Plans - For Inspection
MEPF contractors working on as-built plans; required before occupancy can proceed
GeneralPermit
In Progress CLI / Permits

Area-by-Area Breakdown

Filter: 93 items
Meeting Room
3 Completed 1 In Progress 1 Not Started
ItemCategoryContractorPriorityStatus
Tile threshold for glass doorGlassFASCLADLowCompleted
Operable wall partition
DP pending for delivery
Lacking itemWalls in MotionLowIn Progress
Wallpaper on operable wall partition
GA to install wallcovering after partition is in
Painting/Wall FinishingGAHighNot Started
CCTV Camera — 2 pcs.AuxiliaryNg KhaiLowCompleted
Meeting Room table — 4 pcs.FurnitureTop LineLowCompleted
Huddle Room
2 Completed 2 In Progress
ItemCategoryContractorPriorityStatus
Tile threshold for glass doorGlassFASCLADLowCompleted
Tables — 2 pcs. (1 per room)
3-month lead time
FurnitureCWCHighIn Progress
Glass Door — Huddle Room 2GlassFASCLADHighIn Progress
Office chairs
3-month lead time
FurnitureCWCLowCompleted
Faculty & Director's Room
3 Completed 1 In Progress 0 Not Started
ItemCategoryContractorPriorityStatus
Tile threshold for glass doorGlassFASCLADLowCompleted
TV (to be purchased by UA&P) 32 inch TV installed temporarilyAdditional ItemUA&PLowCompleted
Rectify laminate edging of cabinetsCarpentryGALowCompleted
Glass partition & door — Director's Office
Waiting for glass delivery from China
GlassFASCLADHighIn Progress
Caseroom
18 Completed 4 In Progress 1 Not Started
ItemCategoryContractorPriorityStatus
Rectify door paints, hinges & mechanismsPainting/WallGALowCompleted
Moulding for name labels at tables - needs UAP approval
Graphic Star / KAA inspection this week
CarpentryGAHighIn Progress
Name Labels & Lectern - needs UAP approval
Ongoing proposal
Lacking itemGraphic StarHighIn Progress
Rectify laminate edging of tables & outlet terminationCarpentryGALowCompleted
Nosing of carpet tilesCarpentryGALowCompleted
Acoustic panels — all walls
Pending customs; GA waiting for supplier
Painting/WallGALowCompleted
Chair guard/moulding at wallAdditional ItemGA/UA&PLowCompleted
Auxiliary device — tabletop touch screen
Wall installation ongoing
AuxiliaryNg KhaiLowCompleted
Eraser & chalk holder for blackboardAdditional ItemGA/UA&PLowCompleted
Linear light from Landlite
2-month lead time; expected end of May
ElectricalLandliteMediumIn Progress
Glass for AV Room
Waiting for glass from China
GlassFASCLADHighIn Progress
Ceiling mounted microphone
Needs testing by Manila technician
AuxiliaryNg KhaiLowCompleted
PTZ Camera
To be installed this week
AuxiliaryNg KhaiLowCompleted
Rectify ceiling paint (stains)Painting/WallGALowCompleted
Rectify holes/chipped edges — acoustic ceiling panelCarpentryGALowCompleted
Speaker amplifier reconfiguration
Manila technician from Ng Khai arriving this week
AuxiliaryNg KhaiLowCompleted
Projector screen & accessories
Waiting for device
AuxiliaryNg KhaiLowCompleted
AV Room devices — close ceiling for wiring
Waiting for device
AuxiliaryDATCHELowCompleted
Floor guard at windowsCarpentryGALowCompleted
Door sill at bottomCarpentryGALowCompleted
Fire Extinguisher installation
Needs to be purchased by UA&P first
FireKintarHighNot Started
Switch devices & server for speakers
Additional cost
AuxiliaryNg KhaiLowCompleted
Wheels for podiumFurnitureKAGLowCompleted
Lobby
6 Completed 5 In Progress 2 Not Started
ItemCategoryContractorPriorityStatus
Ceiling mounted speakers — 4 pcs.
Waiting for DATCHE wiring; additional cost
AuxiliaryNg KhaiHighIn Progress
Regrouting of tilesCarpentryGALowCompleted
Biometrics near entrance
Waiting for device
AuxiliaryNg KhaiLowCompleted
FDAS buttons near entrance
Testing functionality
AuxiliaryNg KhaiLowCompleted
Rectify paint of door framePainting/WallGALowCompleted
Signage near entrance -needs UAP approval
Graphic Star to inspect this week; provide render
Additional ItemGraphic Star/UA&PHighIn Progress
UA&P logo on shelves - needs UAP approval
Graphic Star to inspect this week; provide render
Additional ItemGraphic Star/UA&PHighIn Progress
LED Screen — donor wall - needs UAP clear direction
Graphic Star / KAA to provide quotation
Additional ItemGraphic Star/UA&PMediumIn Progress
CCTV Cameras
Needs testing and integration
AuxiliaryDATCHELowCompleted
Furniture — sofa set, lounge chairs, coffee & side tables
3-month lead time
FurnitureCWCHighIn Progress
Adjust pendant light height (+0.1m)ElectricalKintarLowCompleted
Fire Extinguisher installation
To be purchased by UA&P; installed by Kintar
FireKintar/UA&PHighNot Started
Additional switch device for lobby speakers
Additional cost
AuxiliaryNg Khai/UA&PHighNot Started
Restroom
4 Not Started
ItemCategoryContractorPriorityStatus
Tissue holder
To be purchased by UA&P
Additional ItemKintar/UA&PMediumNot Started
Hand dryer
To be purchased by UA&P
Additional ItemUA&PMediumNot Started
Cleaning equipment
To be purchased by UA&P
Additional ItemUA&PMediumNot Started
Exhaust fan
Additional cost; by Kintar
Additional ItemUA&PHighNot Started
Pantry
2 In Progress 2 Not Started
ItemCategoryContractorPriorityStatus
Rangehood installation - Kintar will install the outlet;GA will install the rangehood
Kintar collecting from CLI warehouse
Lacking itemKintarMediumIn Progress
Microwave & RefrigeratorLacking itemUA&PHighNot Started
Rectify cabinet laminate edgesCarpentryGALowCompleted
Tables & Chairs
3-month lead time
FurnitureCWCHighIn Progress
Fire Extinguisher installation
To be purchased by UA&P; installed by Kintar
FireKintar/UA&PHighNot Started
Multipurpose Hall
6 Completed 1 In Progress 3 Not Started
ItemCategoryContractorPriorityStatus
Operable wall partition
DP pending; supplier to do site inspection this week
Lacking itemWalls in MotionHighNot Started
Data floor devices
Additional cost
AuxiliaryNg KhaiHighNot Started
Acoustic panels on wall & chair guard
Waiting for supplier; pending customs
Painting/WallGALowCompleted
Rectify acoustic ceiling panels (chipped edges)CarpentryGALowCompleted
Back glass door
Floor mechanism installed; glass installation this week
GlassFASCLADLowCompleted
Rectify ceiling paint — storage areaPainting/WallGALowCompleted
Light switch — back service areaElectricalKintarLowCompleted
Tables
3-month lead time
FurnitureCWCHighIn Progress
Fire Extinguisher installation
To be purchased by UA&P; installed by Kintar
FireKintar/UA&PHighNot Started
Light switch back service area (Kintar)ElectricalKintarLowCompleted
Server Room
5 Completed 1 In Progress 2 Not Started
ItemCategoryContractorPriorityStatus
Data cabinet & horizontal conduit for internet
PO issued; proceed with PLDT wire installation
AuxiliaryUA&PLowCompleted
Wiring for auxiliary devices
Waiting for device
AuxiliaryDATCHE/Ng KhaiLowCompleted
Rectify sprinkler mountingAuxiliaryDATCHELowCompleted
Rectify wiring near server room entranceElectricalKintarLowCompleted
Fire Extinguisher installation
To be purchased by UA&P; installed by Ng Khai
FireKintarHighNot Started
Internet device - router repeater needs to be installed for the event
Waiting for device
AuxiliaryNg Khai/UA&PMediumIn Progress
Biometrics — back entrance door
Additional cost
Additional ItemNg Khai/UA&PHighNot Started
PLDT Connection (device)- already installed in IDF room PLDT UAP Low Completed
General Notes
5 Completed 3 In Progress 1 Not Started
ItemCategoryContractorPriorityStatus
Rectify cabinet laminate edging — all areasCarpentryGALowCompleted
Rectify drawer runners — all cabinetsCarpentryGALowCompleted
Clean termination — wall covering & all wood cabinetsPainting/WallGALowCompleted
Rectify all painting works — all areasPainting/WallGALowCompleted
Furniture — all areas
3-month lead time
FurnitureCWCHighIn Progress
Occupancy Permit — MEPF As-Built Plans - For Inspection
MEPF contractors working on as-built plans
Lacking itemPERMITS CLIHighIn Progress
Business Permit extension - For Inspection
Infinum working on extension
Lacking itemUA&PHighIn Progress
PLDT Internet connection -
Horizontal conduit PO for wiring
AuxiliaryDATCHE/Ng KhaiLowCompleted
IKEA Bollsidan adjustable laptop tableneeds UAP approval
For speaker's laptop use
AuxiliaryUA&PHighNot Started

Contractor Summary

GA
ID Fitout
29 items
21% Complete
6Done
17Active
6Pending
Ng Khai
Auxiliary Systems
20 items
15% Complete
3Done
14Active
3Pending
FASCLAD
Glass & Glazing
7 items
43% Complete
3Done
4Active
0Pending
CWC
Furniture Supply
6 items
17% Complete
1Done
5Active
0Pending
Kintar
Electrical & Fire
9 items ⚠ At Risk
11% Complete
1Done
1Active
7Pending
Walls in Motion
Operable Partitions
2 items
0% Complete
0Done
2Active
0Pending
UA&P
Owner-Procured Items
12 items ⚠ At Risk
8% Complete
1Done
4Active
7Pending
✓ Watch List saved